KATHMANDU, Nov 23: Nepal and India have taken a significant step towards advancing the 669-megawatt (MW) Lower Arun Hydropower Project, with Prime Ministers Balen Shah and Narendra Modi jointly laying its foundation stone during Shah's official visit to India on Monday.
The Lower Arun project was among four major infrastructure and energy initiatives for which the two leaders virtually laid foundation stones following their bilateral meeting at Hyderabad House. The other projects include an integrated check post at Banbasa, the second phase of the Motihari–Amlekhgunj petroleum pipeline and an oil storage terminal in Jhapa.
The development of Lower Arun is expected to further strengthen Nepal–India cooperation in hydropower development and cross-border energy collaboration. The project is one of the major energy initiatives highlighted during the high-level bilateral engagement.
The 669 MW Lower Arun Hydropower Project, being developed under the Nepal–India energy cooperation framework, will be constructed in Chichila Rural Municipality and Khandbari Municipality of Sankhuwasabha district at an estimated cost of Rs 92.67 billion. The project is targeted for completion within five years.
Compensation distribution for Lower Arun Hydropower Project beg...
The project aims to expand bilateral energy cooperation while increasing Nepal's hydropower generation capacity. It will be developed under the Build-Own-Operate-Transfer (BOOT) model.
Under the Project Development Agreement (PDA), Nepal will receive 21 percent of the project's total electricity generation free of cost. The agreement also stipulates that the project will be transferred to the Government of Nepal without charge after completing 25 years of commercial operation.
The project is being developed through a subsidiary of India's state-owned Satluj Jal Vidyut Nigam (SJVN). The Investment Board Nepal and the project development company signed the PDA on June 1, 2023.
The Lower Arun project will be integrated with the Arun-III Hydropower Project. Under the planned arrangement, water discharged after electricity generation at Arun-III will be diverted through an approximately 17.3-kilometre tunnel to the Lower Arun powerhouse, where it will be used to generate additional electricity.
This arrangement will enable the project to utilise water already used by Arun-III, supporting further hydropower generation through an integrated cascade development approach.
In addition, the two Prime Ministers also jointly inaugurated a motorable bridge connecting Dharchula in India with Darchula in Nepal, as well as a railway service linking Ayodhya with Janakpur.
The project announcements and inaugurations were made during a joint press conference following the bilateral talks. The two countries also exchanged several Memoranda of Understanding (MoUs) covering different areas of bilateral cooperation, reflecting their commitment to expanding economic, energy and infrastructure partnerships.