MAHENDRANAGAR, Nov 24: A budget of Rs 50 million has been sought for the reconstruction of the Dodhara Chandani suspension bridge over the Mahakali River in Kanchanpur, which has remained closed since a flood damaged one of its pillars.
The bridge was damaged by a flood on October 1, completely halting movement across it.
Shankar Budhathoki, chief of the Suspension Bridge Division’s planning section, said the division had initially requested Rs 50 million from the Ministry of Physical Infrastructure Development for the reconstruction of the historic bridge connecting Bhimdatta Municipality and Dodhara Chandani.
Dodhara-Chandani suspension bridge collapses into Mahakali
“We have not been able to deploy technicians to prepare a detailed cost estimate because water is still flowing around the damaged pillar, where soil testing is also required. Once the water level in the river recedes, we will complete the remaining technical work and proceed with the tender process,” Budhathoki said.
A two-member technical team led by Kamal Kumar Adhikari, deputy director general of the Suspension Bridge Division, had visited Kanchanpur to assess the damage.
The team estimated that the bridge had suffered damage worth around Rs 70 million and that approximately Rs 200 million would be required to reconstruct it and bring it back into operation.
The technical team also found that two additional pillars on either side of the collapsed pillar were in a weakened condition.
Meanwhile, the Sudurpaschim provincial government has allocated Rs 10 million for the bridge’s reconstruction.
The Dodhara Chandani suspension bridge is also recognised as a popular tourist destination in Nepal.